Civil Engineering Construction in Sri Lanka
Employer – CBL Foods International (Pvt) Ltd.
Engineer – CBL Corporate Services (Pvt) Ltd.
Contract Value – Rs. 35,656,536.80
Contract Period – 10 Days
Roof Area – 8700sqm
Scope of Work
This project was successfully completed as a special requirement by CBLF New Year festival factory shutdown period. We have successfully planned and organized this project with 120nos manpower and 4 nos of 25-ton mobile Crain’s. The project was done facing adverse weather conditions and day and night basis. Our project scope is Preliminaries, Removing of Existing Zn/Al Roofing Sheets, Glass wool & GI Mesh, Re Strengthen of Roof Structure with ‘C’ Purlins, Installation of 50mm Thick Rockwool Sandwich Panels, Water Proofing and Fiber Works for 80 Nos of Ventilators, Gutters, Down Pipes and Flashings